RENEWABLE ENERGY
Get all the information you need to generate your own clean energy.


























SELF CONSUMPTION (SELCO)
-
About
Apart from Net Metering, SELCO is another option for you to generate electricity from your own solar PV system and thus reduce your electricity bills. SELCO lets you consume all the electricity generated by your solar system, but no excess energy is allowed to flow into the utility network.
The new revised SELCO Guideline (GP/ST/No.51/2024(Pin.2025) published on 23rd of March 2025 specified new criteria for SELCO application.
For Grid-Connected System under Non-Domestic Consumer, no capacity limit is set on the solar PV installation. While for Domestic Consumer the capacity of the solar PV installation shall not exceed:
- 5kW for single-phase 230V supply; or
- 12.5kW for three-phase 400V supply.
All SELCO consumer shall inform TNB on the installation of the Solar PV System by submitting a copy of the SELCO Form of Information via email to RE@tnb.com.my prior to the installation of the Solar PV System.
For Non-Domestic Consumer with capacity more than 72kWp, it is required to conduct Connection Assessment Study (CAS) for the purpose to assess the effect and safety of solar PV installation to the Grid System. The CAS report shall be submitted to TNB via email for obtaining approval for the next process.
For Non-Domestic Consumer with capacity above 72kWp, it is required to have a generation license granted by Energy Commission under the Electricity Supply Act 1990 [Act 447]. Consumer is also required to submit the SELCO Form of Information of Solar PV Installation and related documents to Energy Commission before the commissioning of the solar PV installation.
The installation of a Battery Energy Storage System (BESS) shall only be required after 31st December 2025 for the purpose to reduce the impact of intermittent energy production of the Solar PV System on the Grid System.
For Non-Domestic Consumer with capacity 72kWp and below, consumers are required to submit the following documents to Energy Commission within thirty (30) days after commissioning of the solar PV installation:
- Form of Information of Solar PV Installation
- A copy of Supervision and Completion Certificate (Form G) and Test Certificate (Form H) of the solar PV installation duly signed by the Competent Person.
For Off-Grid system, kindly to consult with Energy Commission for the details requirements.
For information regarding licensing requirements, please refer to www.st.gov.my.
-
How to Apply
STEP 1
Find your registered contractor/ service provider (RC/SP)
STEP 2
Perform and submit CAS report for approval to TNB, if your generated capacity is equal to or more than 72kWp
STEP 3
Submit Form of Information to TNB prior to the installation of the Solar PV System
STEP 4
Apply for generation license from Energy Commission (for capacity above 72kWp)
STEP 5
Your (RC/SP) will install solar PV System
STEP 6
Submit Form of Information and relevant documents to Energy Commission within thirty (30) days after commissioning the solar PV installation (for capacity above 72kWp)
STEP 7
Submit all SELCO documentations to TNB for obtaining TNB SELCO Welcome Letter.
Get In Touch
If you have a specific question regarding SELCO, please contact us at re@tnb.com.my.
Refer to SELCO guideline and to download the SELCO Form of Information here.
Note:
SELCO guideline and form link here.